Scope of Work
Safely change out the floor in the time allocated during major shutdown, including project management and supervision of miscellaneous contractors
Project Resourcing
The project work was carried out onsite by a small team of specialist welders, day and night shift
Project Achievements
- No recordable incidents or injuries = zero harm
- Project delivered ahead of time and under budget
- Hours worked 2,698
- Project schedule delivery 29.11.2012 – 4.30am
- Project actual delivery 24.11.2012 – 18.00pm
- Project Value / Budget $400K
- Project Actual Cost $375K (Provisional)
Activities
Installation of new access door and Tank Floor Replacement – 304 stainless steel material