Client
BGC/Siganto-Stacey
Location
Sir Charles Gairdner Hospital
Project
Air Conditioner Duct Installation
Project Value
Up to $250k
Service
Capital Works & Upgrades, Process Pipe Fabrication & Installation, Specialised Welding & Fabrication
Scope of Work
To fabricate and install Stainless Steel Air Conditioner Duct for Sir Charles Gairdner (Path west) containment facility. The facility has strict decontamination operational procedures due to the testing of Biological, Unusual and foreign disease. All of the system had to pass a PC3 standard. Once passed it would be government assessed and awarded to be a DAFF licenced facility.
Project Resourcing
The project work was carried out offsite by the team at our Henderson fabrication facility and onsite by the APMS Group shutdown management and execution team.
Project Achievements
- No recordable incidents or injuries = zero harm
- Project was delivered on time and on budget
- Site Team was able to overcome difficult tasks of joining pipe work between multi levels
- All pipework and components passed PC3 Standard
- Project was awarded DAFF Licence
Activities
- Workshop stainless steel fabrication
- Workshop pressure testing
- Logistics
- Site fit up
- Site final weld tie–ins
- Site pressure and vacuum testing
- Pipe work passivation
Sir Charles Gairdner Hospital Path West facility for testing